A project consists of the following four activities with activity times in days:
A project consists of the following four activities with activity times in days:    Table CC -Using table CC,what is the crash cost per day for activity B? A) 100 B) 200 C) 250 D) 300 Table CC
-Using table CC,what is the crash cost per day for activity B?