A defence contractor has just started producing engines for a new government contract.The first engine took 800 hours to produce.If the learning curve is 80%,how long will it take to produce the first 20 engines? (Use at least three decimals in the exponent if you use the logarithmic approach,or use Table E.3 cumulative coefficient. )