The Jobs Listed Below Needed to Be Completed

question 73

Multiple Choice

The jobs listed below needed to be completed.Assume that it is now day 140.If the jobs are sequenced according to shortest processing time rule,what is the average completion time? The jobs listed below needed to be completed.Assume that it is now day 140.If the jobs are sequenced according to shortest processing time rule,what is the average completion time?   A) 47.6 days B) 60.2 days C) 94.0 days D) 2.5 days E) 238.0 days