Which of these is not part of the planning files of a production planning and control system?
Delivery Cycle Time
The total time taken from receiving a customer order to the delivery of the product or service.
Complete Orders
The total orders that have been fully processed and are ready for delivery or have been delivered to customers.
Throughput Time
The total time it takes for a unit to go through production from the start to the end, including both processing and waiting times.
Fill Orders
The process of completing a customer's purchase order by preparing and dispatching the ordered goods.
Q6: Define maintenance.
Q36: A linear programming problem has two constraints
Q36: For the lot-sizing technique known as lot-for-lot
Q37: Top executives tend to focus their attention
Q48: Consider the following bill of material.Fifty units
Q73: One of the demand options of aggregate
Q101: Identify sources of variability.
Q103: How is MTBF related to FR(N)?<br>A)MTBF is
Q105: Gross material requirements do not take into
Q158: Demand for dishwasher water pumps is 8