A firm is planning to set up an assembly line to assemble 40 units per hour,and 57 minutes per hour are productive.The time to perform each task and the tasks which precede each task are:
a.Draw a network diagram of precedence relationships.
b.Compute the required cycle time per unit in minutes.
c.Compute the theoretical minimum number of workstations required to produce 40 units per hour.
d.Balance this line using longest processing time.
e.What is the efficiency of the line obtained in part d?
New Dealers
Advocates of the policies of President Franklin D. Roosevelt designed to combat the Great Depression during the 1930s through a series of social and economic reforms.
Unions
Organizations formed by workers to protect their rights and interests through collective bargaining.
Big Corporations
Large and influential companies that possess substantial market power and resources, often operating on a global scale.
Old Age Pension
A regular payment made by a government or a financial institution to individuals who have reached retirement age.
Q30: FedEx chose Memphis,Tennessee,for its central location,or "hub,"
Q30: A tortilla chip workstation produces 1,000 chips
Q36: In supply-chain management,ethical issues<br>A)are particularly important because
Q66: What describes a system that stores and
Q70: Suppose that the allowance factor for a
Q76: Which of the following is usually not
Q109: Work sampling and time studies are similar
Q124: Which distribution system is the fastest growing
Q126: Which of the following is an advantage
Q168: If a manager conducting a time study