Two Critical Path Activities Are Candidates for Crashing on a CPM

question 90

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) One;$400 B) One;$6,800 C) Two;$1,000 D) Two;$5,000 E) One or two should be crashed;$1,400


Definitions:

French Fries

Strips of potatoes that are deep fried until crisp and are often served as a side dish or snack.

Honda Valkyrie Rune

A specific model of a large, luxury cruiser motorcycle produced by Honda, known for its unique design and powerful engine.

Optimal Consumption Rule

The principle that consumers maximize their utility when the ratio of the marginal utility to the price of goods is equal across all goods.

Maximizing Utility

The process by which individuals allocate their resources to obtain the highest possible level of satisfaction.

Related Questions