The network below represents a project being analyzed by Critical Path Methods.Activity durations are A = 5,B = 2,C = 12,D = 3,E = 5,F = 1,G = 7,H = 2,I = 10,and J = 6. a.What task must be on the critical path,regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
e.What is slack time at activity H?
f.What is the Late Finish of activity H?
g.If activity C were delayed by two time units,what would happen to the project duration?
Q1: _ forecasts address the business cycle by
Q7: _ is doing the job properly with
Q19: Which of the following statements is true?<br>A)The
Q24: Relatively few new product ideas,perhaps only 1
Q34: Which of the four major categories of
Q40: Simulation provides optimal solutions to problems.
Q69: The Belgian discount food retailer Franz Colruyt
Q84: Which of the following statements regarding the
Q114: A network consists of the following list.Times
Q123: ISO 9000 seeks standardization in terms of<br>A)products.<br>B)production