The network below represents a project being analyzed by Critical Path Methods.Activity durations are A = 5,B = 2,C = 12,D = 3,E = 5,F = 1,G = 7,H = 2,I = 10,and J = 6. The network below represents a project being analyzed by Critical Path Methods.Activity durations are A = 5,B = 2,C = 12,D = 3,E = 5,F = 1,G = 7,H = 2,I = 10,and J = 6.   a.What task must be on the critical path,regardless of activity durations? b.What is the duration of path A-B-E-H-J? c.What is the critical path of this network? d.What is the length of the critical path? e.What is slack time at activity H? f.What is the Late Finish of activity H? g.If activity C were delayed by two time units,what would happen to the project duration? a.What task must be on the critical path,regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
e.What is slack time at activity H?
f.What is the Late Finish of activity H?
g.If activity C were delayed by two time units,what would happen to the project duration?


Definitions:

Payees

Individuals or entities to whom money is to be paid or is owed.

Discrepancy

A lack of compatibility or similarity between two or more facts, figures, or findings leading to a deviation from what is expected or agreed upon.

Numeric Field

A field in databases or software applications designated for numerical data.

Description Line

A specific line of text that provides detailed information about a product, service, or document, often found in catalogs, invoices, or online listings.

Related Questions