Three Critical Path Activities Are Candidates for Crashing on a CPM

question 67

Essay

Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.    a.What is the crash cost per unit time for activity A? b.What is the crash cost per unit time for activity B? c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost? d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost? e.Assuming no other paths become critical,how much can this project be shortened at what total added cost? a.What is the crash cost per unit time for activity A?
b.What is the crash cost per unit time for activity B?
c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
e.Assuming no other paths become critical,how much can this project be shortened at what total added cost?


Definitions:

Fluid Intelligence

The ability to think abstractly, reason quickly, and solve problems in novel situations, independently of acquired knowledge.

The Bell Curve

A book that argues intelligence is a significant predictor of personal outcomes such as income, job performance, and education, and discusses variations across different racial and ethnic groups.

African Americans

A term referring to citizens or residents of the United States who have total or partial ancestry from any of the black racial groups of Africa.

Heredity

The passing on of physical or mental characteristics genetically from one generation to another.

Related Questions