Two Critical Path Activities Are Candidates for Crashing on a CPM

question 90

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) One;$400 B) One;$6,800 C) Two;$1,000 D) Two;$5,000 E) One or two should be crashed;$1,400


Definitions:

Circular Reasoning

A logical fallacy in which the argument's conclusion is supported by premises that assume the conclusion's truth.

False Cause

A logical fallacy where a cause is incorrectly identified for an event or phenomenon, leading to incorrect conclusions.

Gambler's Fallacy

The erroneous belief that if a particular event occurs more frequently than normal during a past period, it is less likely to happen in the future (or vice versa).

Utilitarian

A philosophy or ethical theory that advocates for actions that maximize happiness and well-being for the majority.

Related Questions