Two Critical Path Activities Are Candidates for Crashing on a CPM

question 88

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) B;$2,000 B) B;$8,000 C) C;$1,000 D) C;$2,000 E) C;$6,000


Definitions:

Self-Efficacy

An individual's belief in their own capability to execute behaviors necessary to produce specific performance attainments.

Opportunity Recognition

The ability to identify and assess potential business or growth opportunities in the market or environment.

Idea Generation

The creative process of generating new, innovative ideas for potential solutions, products, or improvements.

Formal Methods

Rigorous software and systems design methods used to model, specify, and verify the correctness of systems through mathematical techniques.

Related Questions