The First Unit of a Product Took 80 Work Days

question 66

Multiple Choice

The first unit of a product took 80 work days.The learning curve is estimated to be 90%.The time for the fourth unit will be about ________ work days and the time for the first four units will be about ________ work days.(Use Table E.3)