A Defense Contractor Has Just Started Producing Turbines for a New

question 103

Multiple Choice

A defense contractor has just started producing turbines for a new government contract. The first turbine took 7000 hours to produce. If the learning curve is 90%, how long will it take to produce the 10th turbine? (Use at least three decimals in the exponent if you use the formula approach.)