Data Corp.is considering which of 4 different projects to undertake in order to maximize its net present value (NPV) .Define Xi as a binary variable that equals 1 if project i is undertaken and 0 otherwise,for i = 1,2,3,4.The NPV and required capital (in millions) for each project are listed below. Which of the following represents the constraint stating that project 3 can be undertaken only if project 2 is undertaken?