A work cell is scheduled to build 120 digital light processor (DLP)assemblies each week.These assemblies are later installed into home theater projection systems.The work cell has 7.5 hours of productive work each day,six days per week.What is takt time for this cell?


Definitions:

Masters

In an educational context, refers to advanced degrees following a bachelor's degree, such as Master of Arts (M.A.) or Master of Science (M.Sc.), indicating a higher level of study in a particular field.

Demographic Projections

Demographic projections are estimates of future population changes, considering factors like birth rates, mortality rates, and migration patterns.

Racial Minority

Groups of people who are distinguished from the majority population based on race or ethnicity.

United States

A country primarily located in North America, consisting of 50 states, a federal district, five major self-governing territories, and various possessions.

Related Questions