An assembly line with 11 tasks is to be balanced.The longest task is 2.4 minutes,the shortest task is 0.4 minutes,and the sum of the task times is 18 minutes.The line will operate for 600 minutes per day.
(a)Determine the minimum and maximum cycle times.
(b)What range of output is theoretically possible for the line?
(c)What is the minimum number of stations needed if the maximum output rate is to be sought?
(d)What cycle time will provide an output rate of 200 units per day?
Direct Labor-Hours
A measure of the total hours worked directly on a specific product or service by employees.
Predetermined Overhead Rate
An estimated rate used to apply manufacturing overhead to products or job orders, calculated before the period begins based on expected costs and activity levels.
Machine-Hours
A measurement of the amount of time machines are operated during the production process.
Direct Labor-Hours
The total hours worked directly on the production of goods, used as a basis for allocating labor costs to products.
Q5: State the fundamental objective of a firm's
Q9: Lists have been developed that rank countries
Q10: If the schedule calls for the production
Q18: A work system has five stations that
Q23: Which of the following costs would be
Q63: The staff training center at a large
Q106: East Texas Seasonings is preparing to build
Q111: Which of the following are all strategies
Q121: Which of the following statements regarding the
Q123: The Cpk index measures the difference between