Examlex

Solved

The Network Below Represents a Project Being Analyzed by the Critical

question 2

Essay

The network below represents a project being analyzed by the critical path method.Activity durations are A = 5,B = 2,C = 12,D = 3,E = 5,F = 1,G = 7,H = 2,I = 10,and J = 6. The network below represents a project being analyzed by the critical path method.Activity durations are A = 5,B = 2,C = 12,D = 3,E = 5,F = 1,G = 7,H = 2,I = 10,and J = 6.   a.What task must be on the critical path,regardless of activity durations? b.What is the duration of path A-B-E-H-J? c.What is the critical path of this network? d.What is the length of the critical path? e.What is slack time at activity H? f.What is the Late Finish of activity H? g.If activity C were delayed by two time units,what would happen to the project duration? a.What task must be on the critical path,regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
e.What is slack time at activity H?
f.What is the Late Finish of activity H?
g.If activity C were delayed by two time units,what would happen to the project duration?


Definitions:

Assignment

A legal transfer of rights, benefits, or obligations from one party to another.

Quantum Meruit

is a Latin term meaning "as much as he has earned," used in legal contexts to describe the entitlement to be paid for services rendered or work done when no contract exists or where a contract exists but cannot be enforced.

Court-Created Damages

Damages awarded by a court as a remedy in a lawsuit, often in cases where traditional damages are insufficient to resolve the harm done.

Donee Beneficiary

A third party who provides no consideration for the benefits received and who owes the contracting parties no legal duty.

Related Questions