Three Critical Path Activities Are Candidates for Crashing on a CPM

question 78

Essay

Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.    a.What is the crash cost per unit time for each of the three activities? b.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost? c.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost? a.What is the crash cost per unit time for each of the three activities?
b.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
c.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?


Definitions:

Marsupials

Members of the mammal infraclass Marsupialia, characterized by birthing relatively undeveloped offspring that often complete their development in the maternal pouch.

Habitat Loss

The destruction, degradation, and fragmentation of natural environments, leading to a decline in biodiversity.

Physical Environment

The natural and physical surroundings in which organisms live, including land, water, atmosphere, and climate conditions.

Cambrian Explosion

A significant event approximately 541 million years ago, characterized by a rapid diversification of life and the appearance of most major groups of animals.

Related Questions