The Critical Path for the Network Activities Shown Below Is

question 120

Multiple Choice

The critical path for the network activities shown below is ________ with duration ________. The critical path for the network activities shown below is ________ with duration ________.   A) A-D-E;5 B) B-E;6 C) B-D-E;7 D) A-C-E;10 E) B-C-E;12