The Critical Path for the Network Activities Shown Below Is

question 52

Multiple Choice

The critical path for the network activities shown below is ________ with duration ________. The critical path for the network activities shown below is ________ with duration ________.   A) A-C;12 B) A-D-E;19 C) B-E;13 D) A-B-C-D-E;29 E) none of the above