A&C Distributors is a company that represents many outdoor products companies and schedules deliveries to discount stores,garden centers,and hardware stores.Currently,scheduling needs to be done for two lawn sprinklers,the Water Wave and Spring Shower models.Requirements for shipment to a warehouse for a national chain of garden centers are shown below.
Let Sij be the number of units of sprinkler i shipped in month j,where i = 1 or 2,and j = 1,2,or 3.Let Wij be the number of sprinklers that are at the warehouse at the end of a month,in excess of the minimum requirement.
a Write the portion of the objective function that minimizes shipping costs.
b. An inventory cost is assessed against this ending inventory. Give the porti on of the objective function that represents inventory cost.
There will be three constraints that guarantee, for each month, that the total number of
c. sprinklers shipped will not exceed the shipping capacity. Write these three constraints.
There are six constraints that work with inventory and the number of units shipped, making
d. sure that enough sprinklers are shipped to meet the minimum requirements. Write these six constr aints.
Accounts Receivable Turnover
A financial metric that measures how frequently a business can convert its accounts receivable into cash over a specific period.
Inventory Turnover
Inventory turnover is a ratio showing how many times a company's inventory is sold and replaced over a period, indicating the efficiency of inventory management.
Operating Cycle
The period between the acquisition of inventory by a business and the collection of accounts receivable generated from the sale of that inventory.
Acquisition Of Inventory
The process through which a business purchases goods to be sold, which may be raw materials for manufacturing or finished goods for resale.
Q6: For an M/M/k system,the average number of
Q10: Daily demand for packages of five videotapes
Q14: Computer-generated random numbers are not technically random.
Q24: Which of the following is the most
Q24: For an M/M/1 queuing system,if the service
Q26: At the optimal order quantity for the
Q40: A project network is shown below.Use a
Q40: The assumption that arrivals follow a Poisson
Q42: When activity times are uncertain,total project time
Q52: A table of uniformly distributed random numbers