The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client.Accordingly,she has estimated the time it should take for each of her top consultants-Charlie,Gerald,Johnny,and Rick-to complete any of the four projects,as follows:
(a)What is the total number of hours required by the following arbitrary assignment?
Charlie→B;Gerald→A;Johnny→D;Rick→C
(b)What is the optimal assignment of consultants to projects? (Use the assignment method. )
(c)For the optimal schedule,what is the total number of hours it will take these consultants to complete these projects?
Q18: A scheduler may find that freezing the
Q29: Four A washers,five B washers,two C bolts,and
Q53: Compare the assumptions of the production order
Q57: Which of the following statements about maintenance
Q58: What is the objective of scheduling?<br>A)maximize quality<br>B)minimize
Q68: Osprey Fabrication has the following aggregate demand
Q91: Employee empowerment is unnecessary in the Toyota
Q95: A product has a reorder point of
Q108: Lead time for computers is 5 days
Q134: A local artisan uses supplies purchased from