Product A is made from 2 Bs and 1 C.Lead times for A,B,and C are 2,3,and 2 weeks respectively.Currently there are 2 Bs and a 5 Cs on hand,with 5 of each scheduled to arrive at the end of week 1.If 20 As are needed during week 4,can the order be completed (it is the start of week 0 currently)?