Develop a solution for the following line balancing problem,allowing a cycle time of 5 minutes.
a.Draw the precedence diagram for the set of tasks.
b.Calculate the theoretical minimum number of workstations.
c.Balance this line using the longest task time heuristic.
d.What tasks are assigned to which stations?
e.Does the solution have the minimum number of stations? Explain.
f.How much idle time is there,summed over all workstations?
g.What is the efficiency of this line?
Conditional Probability
The likelihood of an event or outcome occurring, given that another event has already occurred.
Given Event
An occurrence or outcome within a probability space that has a specified probability attached to it.
Independent Events
Two or more events whose outcomes do not affect each other, meaning the occurrence of one event does not change the probability of the other.
Probability
A measure of the likelihood that an event will occur, expressed as a number between 0 and 1, where 1 indicates certainty.
Q42: Control charts for variables are based on
Q43: The x-bar chart,like the c-chart,is based on
Q50: The goal of inspection is to:<br>A)detect a
Q62: What are five advantages of work sampling
Q63: Heuristics are problem-solving procedures that mathematically optimize
Q74: What is the difference between P and
Q87: A highway contractor needs to locate a
Q106: One guideline for determining the arrangement and
Q107: Why do modern operations managers look for
Q114: The typical goal used when developing a