A company is trying to balance production between 3 workstations on an assembly line. Currently there are 5 tasks that need to be performed. These tasks, ABCDE, have required times of 2 minutes, 4 minutes, 1 minutes, 3 minutes, and 10 minutes, respectively. The assembly line needs to produce 40 units per day to meet demand and can work for up to 8 hours each day.
(a) What is the required cycle time?
(b) What is the theoretical minimum # of workstations?
(c) Assign the tasks according to the shortest task time heuristic.
Long Term
Relating to a period of time that extends far into the future; often in contrast to short-term or immediate.
Operant Conditioning
A developmental procedure where the force of a response is changed by either encouragement or discipline.
Classical Conditioning
An educational method happening via the connections between a stimulus present in the environment and a stimulus that happens naturally.
Understanding Behavior
The process of interpreting and comprehending actions or reactions of individuals, usually within psychological or sociological contexts.
Q1: _ is the grouping of a variety
Q6: Which one of the following distribution systems
Q12: Which of the following describes using one
Q39: When Daimler and BMW pooled resources to
Q39: In location decisions,intangible costs are easier to
Q41: Statistical process control charts:<br>A)display the measurements on
Q42: What value of the bullwhip measure would
Q48: Psychological factors have little relevance in the
Q55: _ is actual output as a percent
Q143: The work cell layout,a special arrangement of