Two Critical Path Activities Are Candidates for Crashing on a CPM

question 31

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) One;$400 B) One;$6,800 C) Two;$1,000 D) Two;$5,000 E) One or Two should be crashed;$1,400


Definitions:

Bonds Payable

Long-term liabilities representing money a company owes to bondholders, to be repaid at a specific future date, along with interest payments.

Discount Account

An account used in bookkeeping to record reductions in the list price of something, such as merchandise sold or loans issued.

Bonds Payable

Long-term debt instruments issued by a company to raise capital, with a promise to pay back the principal along with interest on specified dates.

Balance Sheet

A financial statement that summarizes a company's assets, liabilities, and shareholders' equity at a specific point in time, giving a snapshot of its financial condition.

Related Questions