Three Critical Path Activities Are Candidates for Crashing on a CPM

question 52

Essay

Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.    a.What is the crash cost per unit time for activity A? b.What is the crash cost per unit time for activity B? c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost? d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost? e.Assuming no other paths become critical,how much can this project be shortened at what total added cost? a.What is the crash cost per unit time for activity A?
b.What is the crash cost per unit time for activity B?
c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
e.Assuming no other paths become critical,how much can this project be shortened at what total added cost?


Definitions:

Legal Force

the effect or power of law enforced by judicial or governmental institutions to mandate compliance or punish violations.

Mentally Incompetent

A legal status indicating that an individual lacks the mental capacity to manage their own affairs or make important decisions.

Adjudged

Adjudged means to make a formal decision or judgment about something, often used in a legal context.

Prohibited By Law

Activities, actions or substances that are explicitly forbidden by legal statutes.

Related Questions