Two Critical Path Activities Are Candidates for Crashing on a CPM

question 31

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) One;$400 B) One;$6,800 C) Two;$1,000 D) Two;$5,000 E) One or Two should be crashed;$1,400


Definitions:

Divisional Level

Pertains to a specific segment or area of operation within a larger organization, often responsible for their own budgets and strategy.

Futures Contract

A standardized legal agreement to buy or sell something at a predetermined price at a specified time in the future.

Forward Contract

A non-standardized contract between two parties to buy or sell an asset at a specified future time at a price agreed upon today.

Related Questions