Table J.17 A Company Must Take on Seven New Projects. Each Project

question 111

Multiple Choice

Table J.17
A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.
Table J.17 A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.    -Using the information in Table J.17 and Johnson's rule, what is the sequence of projects that minimizes makespan? A)  C-A-D-G-E-F-B B)  C-A-D-B-G-F-E C)  G-E-C-A-D-F-B D)  G-E-F-B-D-A-C
-Using the information in Table J.17 and Johnson's rule, what is the sequence of projects that minimizes makespan?


Definitions:

National Government

Refers to the organization through which political authority is exercised at the national level, encompassing all branches and levels of governance.

Veto

The power of a president or governor to reject a bill proposed by a legislature, effectively preventing it from becoming law without further legislative action.

State Legislation

Laws and statutes that are enacted by the legislative bodies of individual states within a federal system, addressing issues within the state's jurisdiction.

Checks and Balances

A system that ensures no single branch of government becomes too powerful, typically through the ability of different branches to check each other's powers.

Related Questions