Table J.17 A Company Must Take on Seven New Projects. Each Project

question 102

Multiple Choice

Table J.17
A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.
Table J.17 A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.    -Using the information in Table J.17 and Johnson's rule, how much idle time does Team 2 have from the start of the first project through completion of the seventh? A)  2 days B)  3 days C)  4 days D)  5 days
-Using the information in Table J.17 and Johnson's rule, how much idle time does Team 2 have from the start of the first project through completion of the seventh?


Definitions:

Rude Disrespectful

Behavior that is impolite, discourteous, or offensive to others.

Energy Level

A measure of the physical or mental vitality or capacity for activity one has.

Taking Care

The act of looking after someone or something to ensure their well-being.

Strategies

General plans or sets of actions aimed at achieving specific goals or solving particular problems.

Related Questions