A production manager is making a decision on batch size for a product with an annual demand of 25,000 units per year. The setup cost for each batch is $45 and once the setup is complete, the product may be produced at the rate of 650 units per day. There is a holding cost of $2 per unit per year and the plant operates on a 250-day production year. How big should the production batch be and how long (in days) will it take to produce the batch?


Definitions:

Cedar Point

An amusement park located in Sandusky, Ohio, known for its large collection of roller coasters.

Plus Sign

A mathematical symbol (+) denoting an operation of addition.

Diagram

A visual representation designed to illustrate or outline the structure of an argument, data, process, or system for clearer understanding.

Premises

Statements or reasons presented in support of a conclusion; in law, can also refer to a house or building, especially one used by a business.

Related Questions