Scenario 4.2 Garman Observes a Worker Assembling Peanut Valves and Records the Records

question 145

Multiple Choice

Scenario 4.2
Garman observes a worker assembling peanut valves and records the data displayed in the table.
Scenario 4.2 Garman observes a worker assembling peanut valves and records the data displayed in the table.    -Use the information in Scenario 4.2.What is the normal time for this job element if the rating factor is 75%? A) 15.06 seconds B) 14.92 seconds C) 13.42 seconds D) 11.19 seconds
-Use the information in Scenario 4.2.What is the normal time for this job element if the rating factor is 75%?


Definitions:

Division's Turnover

A financial metric that measures the revenue generated by a specific division of a company relative to its assets, used to evaluate the division's efficiency in generating sales.

Manufacturing Cycle Efficiency

A performance metric that evaluates the effectiveness of the manufacturing process, focusing on the proportion of value-added time to total lead time.

MCE

Manufacturing Cycle Efficiency, a metric measuring the proportion of production time that is value-added.

Net Operating Income

Income from operations after deducting operating expenses but before interest and taxes.

Related Questions