Table 2.6 -Using Table 2.6,what Is the Earliest Completion Time of This

question 78

Multiple Choice

Table 2.6
Table 2.6    -Using Table 2.6,what is the earliest completion time of this project? A) 23 days B) 25 days C) 27 days D) 29 days