The ________ Is a Priority Sequencing Rule That Is Calculated

question 31

Short Answer

The ________ is a priority sequencing rule that is calculated by dividing the time remaining until a job's due date by the total shop time remaining for the job, including the setup, processing, move, and expected waiting times of all remaining operations, including the operation being scheduled.