Table J.17 A Company Must Take on Seven New Projects. Each Project

question 111

Multiple Choice

Table J.17
A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.
Table J.17 A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.    -Using the information in Table J.17 and Johnson's rule, what is the sequence of projects that minimizes makespan? A)  C-A-D-G-E-F-B B)  C-A-D-B-G-F-E C)  G-E-C-A-D-F-B D)  G-E-F-B-D-A-C
-Using the information in Table J.17 and Johnson's rule, what is the sequence of projects that minimizes makespan?


Definitions:

Meal Reduction

The practice of reducing the size or frequency of meals for reasons such as dieting, fasting, or managing food intake for health.

Larger Bowls

Refers to the psychological effect where the size of a bowl or plate can influence one's perception of portion size, often leading to overeating.

Serve

To perform duties or services for another person or organization.

Food Amount

The quantity of food, measured in terms of volume, weight, or caloric intake, which is consumed or required.

Related Questions