A work center has the following six jobs waiting to be processed (all times are shown in days) :
Table 10.10 A work center has the following six jobs waiting to be processed (all times are shown in days) :    -Use the information in Table 10.10. What is the average past due (in days)  using the FCFS rule? A)  fewer than or equal to 2 days B)  greater than 2 days but fewer than or equal to 3 days C)  greater than 3 days but fewer than or equal to 4 days D)  greater than 4 days
-Use the information in Table 10.10. What is the average past due (in days) using the FCFS rule?