Examlex

Solved

Table 7.4 -Using Table 7.4, What Is the Earliest Completion Time for Earliest

question 102

Multiple Choice

Table 7.4
Table 7.4    -Using Table 7.4, what is the earliest completion time for this project? A)  18 weeks B)  19 weeks C)  20 weeks D)  21 weeks
-Using Table 7.4, what is the earliest completion time for this project?