Table 7.9 -Using Table 7.9, What Is the Minimum Time Schedule for Minimum

question 113

Multiple Choice

Table 7.9
Table 7.9    -Using Table 7.9, what is the minimum time schedule for this project? A)  fewer than 8 weeks B)  8 weeks C)  9 weeks D)  more than 9 weeks
-Using Table 7.9, what is the minimum time schedule for this project?


Definitions: