Examlex

Solved

Table 7.9 -Using Table 7.9, If the Project Completion Time Has to Completion

question 35

Multiple Choice

Table 7.9
Table 7.9    -Using Table 7.9, if the project completion time has to be reduced by one week, which of the following activities should be crashed to minimize the extra cost of earlier completion? A)  Activity B B)  Activity E C)  Activity H D)  Activity J
-Using Table 7.9, if the project completion time has to be reduced by one week, which of the following activities should be crashed to minimize the extra cost of earlier completion?


Definitions:

Related Questions