Table 7.13 All Activity Times for the Project Are in Weeks

question 104

Multiple Choice

Table 7.13
All activity times for the project are in weeks.
Table 7.13 All activity times for the project are in weeks.    -Using Table 7.13, what is the critical path of this project? A)  A-D-H B)  C-E-H C)  B-F-G-H D)  C-E-H and B-F-G-H are both critical.
-Using Table 7.13, what is the critical path of this project?