Two Critical Path Activities Are Candidates for Crashing on a CPM

question 49

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) One;$400 B) One;$6,800 C) Two;$1,000 D) Two;$5,000 E) One or two should be crashed;$1,400


Definitions:

Equal Chance

The principle that each participant or subject in a study has an equal probability of being chosen for any given condition or treatment.

Confounding Variable

is an external factor in a research study that may affect the outcome of the experiment, leading to inaccurate conclusions if not controlled.

Intelligence

The ability to acquire, understand, and use knowledge, as well as to engage in abstract thinking and problem-solving.

Recall Events

The process of retrieving information about past events or experiences from one’s memory.

Related Questions