Two Critical Path Activities Are Candidates for Crashing on a CPM

question 38

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) B;$2,000 B) B;$8,000 C) C;$1,000 D) C;$2,000 E) C;$6,000


Definitions:

Total Income

The sum of all wages, salaries, profits, interest payments, rents, and other forms of earnings received by an individual or organization.

Marginal Product

The additional output that is produced by adding one more unit of a particular input, while holding other inputs constant.

Wage Rate

The amount of money paid to an employee per unit of time or output, commonly expressed as an hourly rate.

Diminishing Marginal Product

The property whereby the marginal product of an input declines as the quantity of the input increases.

Related Questions