Given the project within the table below calculate
a.The critical path
b.The minimum project duration
c.The amount of slack for each activity
Given the project within the table below calculate a.The critical path b.The minimum project duration c.The amount of slack for each activity

Explain insider trading and its implications in the financial markets.
Understand the different types of financial instruments and securities, their risk levels, and insurance mechanisms.
Understand the factors influencing dividend policy decisions.
Recognize the validity of arguments for and against a high dividend payout.

Definitions:

Self-actualizing

The realization or fulfillment of one's talents and potentialities, especially considered as a drive or need present in everyone.

Unconditional

Not subject to any conditions, limitations, or exceptions; often used in psychological contexts to describe types of positive regard or love.

Maslow's Hierarchy

A theory in psychology proposed by Abraham Maslow, depicting a five-tier model of human needs, from basic physiological needs to self-actualization.

Belongingness

The human emotional need to be an accepted member of a group.

Related Questions