Two Critical Path Activities Are Candidates for Crashing on a CPM

question 49

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) One;$400 B) One;$6,800 C) Two;$1,000 D) Two;$5,000 E) One or two should be crashed;$1,400


Definitions:

Reclining Figures

This refers to statues, sculptures or other representations of figures lying down, often used in art to depict relaxation, sleep, or death.

Tomb of the Leopards

An Etruscan burial chamber dating from the 5th century BCE, famous for its wall paintings depicting a banquet scene with leopards.

Banquet

A large formal meal for many people, often involving multiple courses and a set menu, typically held for a special occasion or celebration.

Etruscan Cemetery

An ancient burial site associated with the Etruscans, a pre-Roman civilization in Italy, known for their richly decorated tombs and funerary art.

Related Questions