A network consists of the following list.Times are given in weeks.
a.Draw the network diagram.
b.Calculate the expected duration and variance of each activity.
c.Calculate the expected duration and variance of the critical path.
d.Calculate the probability that the project will be completed in less than 28 weeks.
Cultural Conditions
The environment and circumstances influenced by the beliefs, values, customs, and behaviors of a specific group or society.
Organization Design
The process of structuring an organization’s roles, responsibilities, and systems to effectively achieve its goals and objectives.
Artifacts
Physical objects, symbols, or expressions that represent the culture or values of a society, organization, or group.
Procedures
Established or official ways of doing something, typically involving a series of actions or steps to be followed in a consistent order.
Q29: The World Trade Organization helps provide governments
Q39: _ is the expected time between a
Q42: _ forecasts address the business cycle by
Q43: A system is composed of four parts,J,K,L,and
Q62: Which of the following is the best
Q64: Given the project within the table below
Q68: The ES of an activity that has
Q86: Identify,in order,the six steps basic to both
Q113: The number of kanbans should be equal
Q140: Explain,in your own words,the meaning of the