Which of the following are accurate statements concerning MPS,MRP and capacity requirements planning (CRP) ? I) CRP is equivalent to a master production schedule (MPS) .
II) CRP is needed to determine if an MPS is feasible.
III) CRP is an input to MRP.
IV) Planned-order releases from MRP are the inputs for CRP.


Definitions:

Country

A distinct territorial body or political entity recognized as an independent nation.

Tax-transfer Programs

Government initiatives that collect revenue through taxes to fund transfers of money to individuals or groups, often aimed at reducing poverty and inequality.

Agriculture Subsidies

Financial assistance provided by the government to farmers and agribusinesses to supplement their income and manage the supply of agricultural commodities.

Social Security

Social Security is a government program that provides financial benefits to retirees, disabled individuals, and their families.

Related Questions