A firm is planning to set up an assembly line to assemble 40 units per hour, and 57 minutes per hour are productive. The time to perform each task and the tasks which precede each task are:
A firm is planning to set up an assembly line to assemble 40 units per hour, and 57 minutes per hour are productive. The time to perform each task and the tasks which precede each task are:    a. Draw a network diagram of precedence relationships. b. Compute the required cycle time per unit in minutes. c. Compute the theoretical minimum number of workstations required to produce 40 units per hour. d. Balance this line using longest processing time. e. What is the efficiency of the line obtained in part d? a. Draw a network diagram of precedence relationships.
b. Compute the required cycle time per unit in minutes.
c. Compute the theoretical minimum number of workstations required to produce 40 units per hour.
d. Balance this line using longest processing time.
e. What is the efficiency of the line obtained in part d?


Definitions:

Chronic Glomerular Nephritis

A long-term kidney condition involving inflammation and damage to the glomeruli, leading to impaired kidney function.

Renal Failure

A medical condition where the kidneys lose their ability to filter waste and excess fluids from the blood effectively.

Anemia

A state characterized by a lack of sufficient red blood cells or hemoglobin, leading to a pale complexion and fatigue.

Chronic Glomerular Nephritis

A long-term kidney condition characterized by inflammation and eventual scarring of the glomeruli, affecting the kidney's filtering ability.

Related Questions