The Critical Path for the Network Activities Shown Below Is

question 119

Multiple Choice

The critical path for the network activities shown below is __________ with duration __________. The critical path for the network activities shown below is __________ with duration __________.   A)  A-B-D; 10 B)  A-B-E; 11 C)  C-E; 12 D)  A-D-E; 13 E)  A-B-C-D-E; 22