Two Critical Path Activities Are Candidates for Crashing on a CPM

question 6

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity _________ should be crashed first, adding _________ to project cost. Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity _________ should be crashed first, adding _________ to project cost.   A)  B; $2,000 B)  B; $8,000 C)  C; $1,000 D)  C; $2,000 E)  C; $6,000


Definitions:

Random Access Files

Files that allow data to be read or written in any order, as opposed to sequential access where data is read in order.

Offset Value

Refers to the distance or difference in location, often used in computing to specify the position of a data item within a data structure.

Fwrite()

A function in many programming languages used for writing data to a file.

Related Questions