Two Critical Path Activities Are Candidates for Crashing on a CPM

question 48

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) One;$400 B) One;$6,800 C) Two;$1,000 D) Two;$5,000 E) One or Two should be crashed;$1,400


Definitions:

Effective

Achieving desired outcomes or goals with the least waste of time and effort; efficiency in action or use.

Excise Tax

A tax charged on specific goods and services, such as alcohol, tobacco, and fuel.

Government Revenue

The income received by the government from taxes, non-tax sources, and other fiscal policies.

Latte

A latte is a coffee drink made with espresso and steamed milk, often enjoyed in various flavors and styles across coffee shops globally.

Related Questions