Two Critical Path Activities Are Candidates for Crashing on a CPM

question 47

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) B;$2,000 B) B;$8,000 C) C;$1,000 D) C;$2,000 E) C;$6,000


Definitions:

Local Businessperson

A local businessperson is an individual who owns or operates a business within a specific geographic area, serving the needs of their community or region.

Government Clerk

A public sector employee who performs administrative and clerical duties within a government agency.

Airline Baggage Handler

A worker responsible for loading, unloading, and transporting luggage and cargo at airports.

Social Citizenship

The rights and obligations of citizens in a society, particularly concerning social welfare and participation in the social life of the community.

Related Questions